Civil and Structural Piling Specification

CONTENTS

1.     INTRODUCTION

2.     C4-10 BORED PILING

3.     C4-20 DRIVEN PILING

4.     C4-30 PILE TESTING


1    INTRODUCTION

This document presents the specifications for piling works to be used in the project. The specifications found herewith shall supplement SCI’s specification listed below and the Invitation to Bid (ITB) Appendix A: Facilities Description / Scope of Work document. Unless noted otherwise, the more onerous criteria or requirements specified between SCI’s specification and the ITB
Appendix-A document shall take precedence over the conflicting clauses found in this document.



SCI Specification & Standard Document No.

Rev.

Document Title

SUTO-ALL-C08-4-001

1

Specification and Standard: Demolition and Site Clearance

SUTO-ALL-C08-4-002

2

Specification and Standard: Earthworks and Excavation

SUTO-ALL-C08-4-003

1

Specification and Standard: Piling – Driven Piles

SUTO-ALL-C08-4-004

1

Specification and Standard: Structural Steelworks

SUTO-ALL-C08-4-005

1

Specification and Standard: Soil Investigation & Testing

SUTO-ALL-C08-4-006

1

Specification and Standard: Concrete

SUTO-ALL-C08-4-008

1

Specification and Standard: Pipe Rack Design Criteria



In the event that the specifications are not available in either the SCI’s or those found herewith, refer to the latest edition of the National Productivity and Quality Specifications published by SPRING Singapore. The specification list is non-exhaustive and will be expanded if the need arise.


2    C4-10  BORED  PILING

CONTENTS                                                                                                              Page


1.
GENERAL
3
1.1
Scope
3
1.2
Related Sections
3
1.3
Standards and Regulations
3
1.4
Trade Preambles
4
1.5
Definitions
7
2.
PERFORMANCE REQUIREMENTS
8
2.1
Requirements for Design Verification
8
2.2
Performance Criteria for Piles Under Test
8
2.3
Permissible Damage Criteria for Existing Critical Structures or Services
8
3.
MATERIALS
9
3.1
Source of Materials
9
3.2
Drilling Fluid
9
3.3
Water
9
3.4
Concrete
9
3.5
Grout
9
3.6
Reinforcement
9
3.7
Temporary Casings
9
3.8
Permanent Steel Casings
10
4.
WORKMANSHIP
11
4.1
General Workmanship Requirements
11
4.2
Trial Bores
11
4.3
Boring Excavation
11
4.4
Use of Drilling Fluid
13
4.5
Cleanliness of Pile Bases
13
4.6
Reinforcement
14
4.7
Pile Casting
14
4.8
Backfilling Empty Boring
17
4.9
Grouting of Piles
17
4.10
Tolerances
18
4.11
Protection to Piles
19
4.12
Replacement of Piles
19
4.13
Cleaning Up
19
4.14
Non-Performance of Working Piles
19
4.15
Cutting Off Pile Heads
19
4.16
Noise and Disturbance
20
4.17
Final Survey and As-Built Drawing
20
5.
VERIFICATION AND SUBMISSIONS
21
5.1
Submissions
21
5.2
Inspection and Test Certificates
22
5.3
Tests
23
5.4
Compliance Testing of Drilling Fluid
23
5.5
Pile Testing
24
5.6
Records
25
.       GENERAL

Read with the General Requirements section, and all other contract documents.

1.1     Scope

This section covers the requirements for the construction of bored cast-in-place piles including:

a.       In-situ concrete piles b.       Micro piles

The piles may be used as foundations to support principally vertical loads, or may be used to form embedded retaining walls resisting principally horizontal loads.

1.2     Related Sections

Read this work section in conjunction with the relevant requirements of the other work sections as follows:

C1-20   Condition Survey and Monitoring

C2-10   Site Investigations

C2-50   Instrumentation and Monitoring

C4-30    Pile Testing

C3-10    Concrete Construction Generally

C3-20    Reinforcement

1.3     Standards and Regulations

1.3. Standards

Unless otherwise agreed by the Superintending Officer (SO), ensure all of the Works comply with the relevant requirements of the Standards and Codes listed below or referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative Standards and Codes comply with the requirementof  the  standards specified.  All Standards and Codes quoted are the current version, unless specific year references are noted.

Singapore   Standards

SS 31  Aggregates from natural sources for concrete

SS 78: Part A16 Testing  Concrete.  Method  of  determination  of  compressive strength of concrete cubes

SS CP 4     Foundations

SS CP 65: Part 1  Structural use of concrete. Design and Construction

SS CP 79   Safety management system for construction worksites


Other Standards

API SpecificationDrilling Fluid13A 5th Edition

API-RP-13B-1 2nd   Standard procedure for field-testing water-based drilling fluid Edition BS 1305 Batch type concrete mixers

BS EN 1008                     Mixing water for concrete, specification for sampling, testing and assessing the suitability of water

BS 5228                           Noise and vibration control on construction and open sites

Part  1(1997)  Code  of  practice  for  basic  information  and procedures for noise and vibration control

Part 4 (1992) Code of practice for noise and vibration control applicable to piling operation

BS 5930                           Code of practice for site investigations

BS 7123                           Metal arc welding of steel for concrete reinforcement

BS 8004                           Code of practice for foundations

BS 8008                           Guide   t safet precautions   and   procedures   fo the construction and descent of machine-bored shaft piling and other purposes.

BS EN 1538                     Execution of special geotechnical work Diaphragm Walls

In the event that the standards or Codes are revised or superseded, refer to the latest edition or the appropriate substitution for the relevant subjects.

1.3. Technical Reference

Refer to the following technical reference for guidance in carrying out the works:

a.        BRE Digest 251 (1995) Assessment of damage in low-rise building.

b.        Construction Industry Research and Information Association, England (CIRIA) Report 104 (1984) Design of retaining wall embedded in stiff clay.

1.4     Trade Preambles

1.4. Design Verification

Engage technically competent personnel with relevant geotechnical experience to SOs acceptance, to carry out:

a.        Verification of material excavated at the intended pile founding level as consistent with the design requirements.

b.        Design verification checks based on actual ground conditions to determine the required length of each pile and ensure that the specified working load and settlement criteria of the piles are achieved.

c.         Proposals to amend the design including compensating piles as necessary in the event that for any reasons the installed piles do not perform as intended.

d.        Proposals to amend the pilecap design of the building in the event that the piles are installed out of the permitted tolerance.

e.        Proposals as a response plan in the event that measures taken to control ground movement and vibration do not perform satisfactorily.

Take into account of the design requirements as set out in Clause 2.1 below.

Submit the design to the SO for acceptance. Design proposals in (c) to (d) are to be designed and endorsed by a PE (Civil).

Submit the CV of the personnel to be engaged for the above including the PE’s, for SOs acceptance.

1.4. Building Damage Assessment


Carry out a Building Damage Assessment, if required by the project specification, on the effects of ground movement to the neighboring properties due to the works, for the purpose of  establishing suitable  values for  ‘Alert and  Work  Suspension’ levels  for monitoring. Submit to SO with endorsement from a PE.

1.4. Coordination with Other Works

Co-ordinate with other contractors who may carry out other works at the same time at the site. Take into account of site access, space occupation, safety and safeguarding of adjoining properties and each others works.

1.4. Condition Survey

Where applicable, prior to and upon completion of the site works, carry out a condition survey to  adjacent  buildings  in  accordance  with  the  requirementof  section  C1-20 Condition Survey and Monitoring. Submit all records to the SO and adjacent property owners where directed.

Keep a copy of the survey report on site ready for inspection.

1.4. Instrumentation and Monitoring

Provide instrumentation to monitor the ground movement, vibration and condition of adjacent properties. Refer to Section C2-50, Clause 3.1, and the drawings for the schedule of instrumentation required. If necessary or as required by the authorities, propose and provide additional instrumentation and monitoring for records.

Take cognisance of and co-ordinate with other contractors on site who may be carrying out  instrumentation  and  monitoring  workto  avoid  duplication  of  installation  and readings.

For general requirements of the instrumentation and monitoring works refer to Section
C2-50.

1.4. Upholding of Adjoining Properties

Accept responsibility for the upholding of the adjoining buildings and roads, footpaths etc., where applicable, together with the mains and services from the time of taking possession of the site through the duration of the works.

Adequately maintain roads and footpaths within and adjacent to the site and keep clear of mud and debris.

1.4. Verification of Site Information

1.4.7. Site Surveys

Verify  and  be  satisfied  that  the  information  given  in  the  existing  site  survey  plans provided are accurate. If necessary, engage a registered Surveyor to carry out additional site survey before commencing any work.

1.4.7. Additional site investigations

Carry out additional ground investigation where additional information is needed for the works or when directed by the SO. Carry out the works in compliance with Section C2-10 Site Investigation.

Carry out the boreholes progressively prior to commencement of the works in areas according to the contractors construction programme. On completion of drilling, backfill the boreholes with a suitable bentonite / cement mix.

Submit the location and schedule for the boreholes to SOs acceptance prior to carrying out the works. On completion, prepare the site investigation report and submit to the SO for acceptance.

1.4.7. Groundwater level


Verify the data on groundwater level from available ground investigation reports.

1.4.7. Contamination

Verify information on contamination identified or believed to be present on site.

In the event that contamination is either positively identified or suspected, draw to the attention  of  all  personnel  working  on  sittogether  witthe  need  ttake  any precautionary measures in handling contaminated materials, groundwater and obnoxious vapours from the ground.

1.4. Existing Services Affected by the Works

Refer to Preliminaries and Conditions of Contract for the requirements to deal with existing services affected by the works.

1.4. Site Protection

Protect all equipment and working area using fencing or other methods as accepted.

1.4.10 Obstructions

If  any obstructions  such  as  existing  fences,  structuresfootings,  boulders,  concrete blocks, pipes, drains, driveways or ramp are encountered during excavation, submit proposals for their removal for the SO's acceptance.

1.4.11 Supervision of the Works

Engage a competent and suitably experienced site engineer to the SOs acceptance, to supervise the field works.

1.4.12 Quality Control Plan

Submit and work to a quality control plan as agreed with the SO. Refer to the General
Requirements section, clause 1.4.10 for guidance.

1.4.13 Safety

Provide safety precautions to comply with all current legislation and regulations, notably:

a.  Building Control Regulations

b.    Code of Practice for Traffic Control at Work Zone

c. Factories(Building Operations and Works of EngineeringConstruction)Regulations

d.        Workplace Safety & Health Act

e.        SS CP 79 Safety management system for construction worksites

f.         For works within LTA Railway Protection Zone, ensure the works comply fully with Code of Practice for Railway Protection.

Additionally, comply also with the following:

a.        BRE Digest 251 (1995) Assessment of damage in low rise building

b.         BS 8008: Guide to safety precautions and procedures for the construction and descent of machine-bored shaft for piling and other purposes

1.4.14 As-Build Pile Surveys

Employ a Licensed Surveyor who is to be responsible for surveying pile locations and eccentricities and submit the as–build survey to the SO in format as directed within 14 days after the piles have been trimmed to the cut-off level.

1.5      Definitions



a.
Pile Dimensions
Piles dimension specified in pile layout drawing(s) / piling
schedule are the minimum acceptable dimensions
b.
Rock
Material classified as grade I to III in table 10 Scale of
weathering grades of rock mass” in BS 5930: 1981.
2.         PERFORMANCE REQUIREMENTS

2.1       Requirements for Design Verification

The required working load and sizes of the piles are indicated in the drawings, together with an indication of the required pile penetration depth.

Based on actual ground conditions encountered as revealed by boring logs or ground investigations, carry out design check to confirm the required pile length as to achieve the specified  working  load  within  the  specified  limits  for  load  settlement  behaviour  as indicated in Clause 2.2. Account for effects of negative skin friction where applicable.

Verify the design based on SS CP 4 unless otherwise agreed.


2.2      Performance Criteria for Bored Piles

Any of the piles, when under static or dynamic load test, is to satisfy the performance criteria as set out below:


Axial Compression Tests (Ultimate and Working Load)

Pile Type

and Size
Specified
Working Load (Axial Compression)
Permitted Settlements (mm)
(SWL)

(kN)
1.0*SWL

(2nd cycle)
1.5*SWL

(2nd cycle)
2.0*SWL

(2nd cycle)
Residual
Settlement

(End of 2nd
cycle)
900mm
diameter
Bored Pile

1200mm diameter Bored Pile
4550




8500
7




7
15




15
25




25
7




7


In addition, the overall pile capacity in ultimate load tests is to have factors of safety of at least 2.5 against design ultimate compression load, 2.0 against design ultimate lateral load and 3.0 against design ultimate tension load.

2.3      Permissible Damage Criteria for Existing Critical Structure or Services

Based on the results of the damage assessment as set out in Clause 1.4.2, propose the allowable ground settlement and vibration limits due to the works taking into account the vulnerability  and  sensitivity  of  the  adjacent  properties  e.g.  VLCC  (48”  Crude  Oil Pipelines).

State the values for alert and work suspension levels in the submission in accordance with the requirements of Building Control Act [Section 7(2)] Annex (BE/CP/5).

Notwithstanding the above, ensure that the ground movements and vibrations generated by the works comply with the following if more stringent:

a.        Generally comply with the requirements of BS 5228 Part 1.

b.        The vibration generated by the works in MRT structures not to exceed a peak particle velocity of 15mm/s.

c.        Unless otherwise directed, refer to Section C2-50, Clause 4.2.2 for general restrictions on ground movements and vibration limits for adjacent structures where relevant.

d.        Refer to piling drawings for vibration limits.

3.         MATERIALS

3.1       Source of Materials

Do not change sources of supply until it has been demonstrated that the materials from the new source can meet all the specified requirements.

Remove from site any material that fails to comply with the specification.

3.2       Drilling Fluid

3.2.1     General Requirement

Where drilling fluid is used it is to be such as to:

a.        Provide continuous support of the excavation b.        Be easily displaced during concreting
c.        Not pollute the ground at any stage

d.        Not coat the reinforcement such as to impair the steel/concrete bond

Drilling fluid including Bentonite supplied to the site and prior to mixing is to be in accordance with API Specification 13A 5th Edition (1993) Drilling Fluid.

3.3       Water

Water used for the construction is to be clean and free from harmful matter in solution or suspension.

If taken from a source other than the Public Utilities Board, water is to be tested in accordance with BS EN 1008.

3.4       Concrete

Refer to section C3-10, clause 3.0 for general requirement of concrete.

3.5       Grout

Grout containing fine aggregate may be used in place of concrete. Constituents are to be water, ordinary Portland cement, fine aggregate where permitted and admixtures subject to agreement.

3.5.1   Minimum Cement Content
Minimum cement content is to be 390kg/m3  for concrete to be placed under water or drilling fluid by tremie method.

3.5.2   Fine Aggregate

Fine aggregate is to be in accordance with grading C or M of SS 31 (1998) Table 6.

3.6       Reinforcement

Refer to section C3-20, clause 3.0 for general requirements of reinforcement.

3.7        Temporary Casings

Unless otherwise agreed with the SO, temporary casings of accepted quality or an accepted alternative method is to be used to maintain the stability of pile excavation. Propose to SO’s acceptance, the depth, size and thickness of casing to be provided.

Temporary casings are to be free from significant distortion. They are to be of uniform cross-section throughout each continuous length. During concreting they are to be free from internal projections and encrusted concrete, which might prevent proper formation of the piles.

3.8      Permanent Steel Casings

When permanent casings are required, use S275 steel sections in compliance with BS EN 10210.

4.       WORKMANSHIP

4.1     General Workmanship Requirements

Ensure the equipment set up and installation procedures are in conformance with SS CP
4: 2003.

4.1. Depth of Penetration

Install each pile to the designated penetration as indicated in the drawings or as adjusted as a result of the design verification check.

4.1. Socketing of End Bearing Piles

For all piles indicated as end bearing in the drawings or schedules, form a socket of depth at least 1m or 1 times diameter, whichever is larger, into the material that meets the founding conditions, unless indicated in the drawings or modified as a result of the verification check in clause 1.4.1, as approved by the SO.

4.1. Pile Toe

Adopt a construction method, which ensures that the soil below the pile is not softened. Ensure that no drilling fluid or slurry remains at the base of the pile.

4.1. Continuity of Construction

4.1.4. Time for Excavation and Concreting

Each pile is to be excavated and concreted within twenty-four hours from the start of excavation below any temporary casing.

Where this time restraint cannot reasonably be met, set out an alternative in the method statement together with an estimate of the likely effect on the performance and capacity of the pile.

4.1.4. Construction without temporary casing

A pile constructed in a stable cohesive soil without the use of temporary casing or other form of support is to be bored and concreted without prolonged delay and in any case soon enough to ensure that the performance of the pile is not impaired.

4.2     Trial Bores

Conduct trial bores to confirm the ground conditions and the feasibility of the proposed method of installation.

Agree with the SO on the location, depth and size of the trial bores.

4.3     Boring Excavation

4.3. General

Submit a detailed method statement clarifying the procedure for installing the bored piles including the method of overcoming any obstructions encountered and drilling through hard rock for SOs acceptance. The method of excavation is to ensure no soil collapse in the bored holes. Do not commence working pile excavation before method of excavation is accepted.

Carry out boring excavation generally using boring or reversed circulation drilling equipment operating at the existing ground level.

Provide temporary steel casing and drilling fluid if necessary to support the excavation. Ensure the extreme dimensions (teeth to teeth) of the boring bucket or auger is not smaller than the specified pile diameter.

Do not dewater within the excavated bored holes.

4.3.2  Boring Proximity

Do not bore so close to piles that have been recently cast which contain workable or partially set concrete that a flow of concrete or instability could be induced or damage sustained by any previously formed piles.

Boring is to be kept clear from a minimum distance of 5 times pile diameter from a newly cast pile within 24 hours after casting.

4.3. Ground Conditions

Report to the SO immediately any apparent variance in the ground conditions from those reported or might have been inferred from reports.

4.3. Rock Socketing and Obstructions

When socketing through rock had been called for or in the event of encountering obstructions below ground level during boring, use reverse circulation drilling method, chiseling or propose other means for SOs acceptance to bore through the obstruction or rock.

Should  the  reverse  circulation  drilling  method  fail  to  clear  the  obstruction  or  rock, propose and employ other methods including predrilling with coring to assist in the clearing of the obstructions.

4.3. Temporary Casing

Unless otherwise agreed, provide a temporary casing of appropriate size and length to support the excavation. Use low vibration equipment to install and extract casing for bores in built-up areas. Refer to design drawings for vibration limits.

4.3. Pumping from Pile Excavation

Do not pump from a pile excavation unless a casing has been placed into a stable stratum, which prevents the flow of water from other strata in significant quantities into the boring, or unless it can be shown that pumping will not have detrimental effect on the surrounding soil or property.

4.3. Determining Penetration Depth

Verify soil extracted as consistent with design assumptions in accordance with clause
1.4.1 above. Terminate boring at the level indicated in the drawings, subject to modifications as a result of verification check in clause 1.4.1. and to SOs approval.
Keep  soil samples drilled at  strata change and at  2m  intervalfor  records,  unless otherwise indicated in PSD.  The samples shall be  stored in  a  safe place  which  is
sheltered from sunlight and rain.

4.4     Use of Drilling Fluid

4.4. Proposal for Use

Propose to the SOs acceptance on the need to use drilling fluid. If acceptable, propose suitable type and method of drilling fluid to be used.

4.4. Storage

Store solid additives in separate waterproof stores or containers, which will prevent the materials from becoming contaminated.

4.4. Use

Use in accordance with the manufacturers instructions unless there is a demonstrable reason to do otherwise.

4.4. Mixing

Mix drilling fluid thoroughly with clean fresh water to make a suspension, which will maintain the stability of the pile excavation for the period necessary to place concrete and complete construction.

Where saline or chemically contaminated groundwater occurs, take special precautions to modify the drilling fluid suspension or prehydrate the drilling fluid in fresh water so as to render it suitable in all respects for the construction of piles.

4.4. Stability of Pile Excavation Using Drilling Fluid

Where the use of  drilling fluid is accepted for maintaining  the stability of  a boring, maintain the level of the fluid in the excavation so that the fluid pressure always exceeds the pressures exerted by the soils and groundwater. Use an adequate temporary casing in conjunction with the method to ensure stability of the strata near ground level until concrete has been placed.

Maintain the fluid level at a level not less than 2m above the level of the groundwater unless otherwise agreed.

In the event of a rapid loss of drilling fluid from the pile excavation, backfill the excavation without delay and inform the SO immediately. Obtain directions from the SO before excavation at that location is resumed.

4.4. Spillage and Disposal

Take all reasonable steps to prevent the spillage of drilling fluid suspension on the site in areas outside the immediate vicinity of boring. Remove discarded drilling fluid from the site without delay. Disposal of  drilling fluid is to comply with the regulations othe appropriate authority.

4.5      Cleanliness of Pile Bases

On completion of boring and immediately prior to casting, remove all loose, disturbed or remoulded soil or rock from the base of the pile while avoiding disturbance to the ground below the base. Maintain the stability of the bore at all times, using appropriate levels of support fluid as required.




4.6      Reinforcement

4.6. General

Refer to section C3-20, clause 4.0.

4.6. Fixing